Apply for a residential meter connection

Water connections are available to all properties that have direct access to Shoalhaven City Council's water reticulation system.

Residential connections include:

  • A standard metered water service installed at the property boundary which includes an adjacent garden tap; and
  • The option of having the meter installed in a pit (this option will not include a garden tap) 

Steps to apply

Click on the below tabs to find out what you need, how to apply, and what happens next.

Before you apply

Prepare your documentation before you apply

When applying for a residential water meter connection, you’ll need to upload a Service Location Plan — a simple diagram showing where you’d like your meter installed. This helps us position your meter correctly and efficiently. 

Location requirements

Please ensure your nominated meter location:

  • Is positioned along your front boundary, and
  • Is no more than 1 metre inside the front boundary line.

You can upload your Service Location Plan in JPG or PDF format during the application process.

Important note - In some cases, conduit for a long service may already be installed, connecting to a water main located on the opposite side of the street. If your preferred meter location doesn’t align with the existing conduit, additional installation costs may apply. If this happens, we’ll contact you to discuss the costs and explore alternative location options.

How to apply

Complete the online application form

Have your Service Location Plan ready to upload when prompted.

The link below will take you to Council's online request management platform.

Apply online

Please be advised: Due to an influx of connections, an underbore installation will take a minimum of 30 business days.

What happens next

Step 1.Application review

On receipt of application, we will review your service location plan and if viable, issue a payment advice (invoice).

Full payment must be made prior to works commencing.

Step 2.Meter installation

On receipt of payment, we will install the meter in accordance with the approved service location plan (or agreed alternative) within approximately 20 business days. To avoid delays, the site must have a minimum two (2) metre clearance at the installation point.

Please note that weather and site conditions may cause delays beyond the estimated timeframe.

Step 3.Connection to dwelling

All internal pipes on the property including taps and drains, are the property owner’s responsibility. Once the meter has been installed, the property owner or builder must engage a licensed plumber to connect the metered service to the dwelling.

Should a meter be damaged or interfered with, charges may be issued to the property owner.

Need help?

Need help? Contact us today

Call us on (02) 4429 3214 or visit your closest administration centre

Nowra Administration Centre
Opening hours: Monday to Friday, 9:00am to 4:00pm
36 Bridge Road, Nowra NSW 2541

Ulladulla Branch Office
Opening hours: Monday to Friday, 10:00am to 2:00pm
14 Deering Street, Ulladulla NSW 2539

Service location plan example

Here is an example of a residential service location plan.

Please be reminded that your preferred location must be along the front boundary of the property. 

If your preferred location does not line up with an existing conduit, we will contact you to discuss costs and possible alternative service location options.

example service location plan for residential dwelling